The Beulah/University Realignment Project is an improvement project undertaken by the City of Flagstaff and Eagle Mountain Construction
Project Details
Phase 1 of this project began on April 3rd, 2023.
The final portion of Phase 1 includes crossing Milton Road with new water and sewer utility infrastructure, which began April 8, 2024.
Phase 1
Extending present-day Beulah Boulevard northward to present-day University Avenue, with a roundabout constructed at the new intersection
Realigning present-day University Avenue, east of the new roundabout, to match up with University Drive, east of Milton Road
The installation of fiber optic conduit, stormwater infrastructure improvements and sewer and water pipe-upsizing between Knoles Drive and Milton Road, within the Milton/University intersection and the southwest section of the Target parking lot
Phase 2
Constructing a pedestrian underpass just north of the Milton Road/University Drive intersection (between Burger King and Target)
Surface improvements along Milton Road as highlighted in the map
Motorists, pedestrians and bicyclists can expect traffic delays, lane closures and detour routes along Milton Road, University Drive and University Avenue until late 2025. Crews will work to maintain core public services (mail, trash services, emergency access, etc.) and access to driveways at all times throughout the project. The City and contractor will ensure continuous water service to all properties over the duration of the project, however, brief water shut-offs will be required to tie into the City’s existing system. Those affected will be notified in advance of any temporary utility interruption.